Adobe Creek Sewer Main Replacement

Project ID: 
WW-01012
Project Category: 
Sewer
Project Status: 
Not Started
Project Priority: 
Asset Preservation
Project Lead: 
A. Fairman
Year Adopted:
2020
Target Completion Date:
2026

This project scope includes replacing, and for some segments realigning, fifty-three sewer main segments, located along or near Adobe Creek.  This comprises a total of 6,580 linear feet of pipe replacement.  The existing 6-inch and 8-inch pipes will be replaced with new 8-inch pipe to increase capacity. The sewer line segments identified for this project are located near the City’s border with the Town of Los Altos Hills, north of Manresa Avenue and south of Edith Avenue.  

Project Estimates

Prior
Appropriations

2020/21 Budget 2021/22 Planned 2022/23 Planned 2023/24 Planned Total
Adobe Creek Sewer Main Replacement $0 $500,000 $0 $0 $0 $500,000
Funding Sources            
Sewer Fund $0 $500,000 $0 $0 $0 $500,000

 

Adobe SSMH
Adobe SSMH
Adobe SSMH
Adobe SSMH